Downtown Utility Infrastructure Improvements

Featured Links

Subscribe to CitE-News
Downtown Infrastructure Improvements Project
Northeast Infrastructure Improvement Project
Pay Your Bills Online
Customer Comment Card

Other Resources

USA.gov Virginia.gov
2-way traffic coming soon

Downtown Utility Infrastructure Improvements


DUII Survey

October 23, 2009

This afternoon, the final concrete base was poured for the sidewalk base. This activity concludes the underground utilities infrastructure improvements on Cameron and Braddock Streets in Winchester. The City’s contractor DLB, Inc. met the October 24, 2009 deadline a day ahead of schedule.

  • Below is the target paving schedule for next week (October 26-October 30). Every attempt will still be made to keep one lane open to allow for traffic movement during the paving (dates are subject to change if we have bad weather, break downs, etc.):
    Monday - leveling course on Cameron Street from Cork Street to Fairfax Lane.
  • Tuesday - final layer of surface course of asphalt on Cameron Street from Cork Street to Fairfax Lane.
  • Wednesday - tie-in surface course of asphalt at the corner of Braddock Street & Cork Street for cross walks.
  • Thursday-Friday -tie-in the other intersecting streets along Braddock Street.

On the first weekend in November (if weather allows), the City will celebrate the end of the Cameron and Braddock Street phase of the Downtown Utility Infrastructure Improvement (DUII) project and dedicate the two-way traffic.

Be on the look out for the upcoming citizen survey! The City wants to know your thoughts about the DUII project and how we can improve for Phase II of the project. Phase II of the DUII project will include Piccadilly Street. This phase will not begin until after the holidays on January 4, 2010.

October 13, 2009

  • The final paving on Braddock Street is occurring this week!!  The brick sidewalks on Braddock are nearing completion.
  • All the new water main installation is complete on Cameron.  All the remaining underground utility installations should be completed this week.
  • The contractor is working diligently to complete all the concrete work and patching all the trenches with asphalt before their deadline which is the end of next week.
  • The signal contractor is working on activating the new traffic signals on Braddock and Cameron.
  • We are still on schedule to convert Braddock and Cameron to two-way traffic before Thanksgiving.  Additional details will be provided as we get closer to the two-way conversion.  Our current plan is to make the conversion on a Saturday/Sunday in November.
  • Work on Piccadilly Street is scheduled to begin January 4.

 

August 31, 2009

The progress on the project the past month has been excellent and we are still on schedule to complete the work on Braddock and Cameron by October 24.  On Braddock Street, crews are finishing the installation of the storm drain pipe between Amherst and Piccadilly which is the final component of the underground infrastructure on Braddock.  On Cameron Street, all of the underground utility installation south of Cork has been completed.

The photos below show the base layer paving on Braddock Street which occurred this week.  This is certainly a welcome sight by everyone and sign that we are getting closer to completion.

CLICK IMAGES FOR LARGER VIEW

August 3, 2009

The installation of the new sidewalks on Cameron Street started in earnest the past two weeks.  Already, the new sidewalks have been installed between Gerrard and Monmouth.  The end of July marked the halfway point regarding the schedule to complete the work on Braddock and Cameron by the end of October.  The photos below show the new sidewalks on Cameron.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished past two weeks:

  • 17 sewer laterals replaced (approximately 425 feet of 4-inch PVC pipe)
  • 4 sanitary sewer manhole replaced
  • 315 linear feet of 8-inch+ sewer main
  • 250 linear feet of 8-inch+ water main installed
  • 7 new water valves installed
  • 38 water service lines replaced (approximately 1,087 linear feet of copper tubing)
  • 2 new fire hydrants installed
  • 6 stormwater structures installed
  • 470 linear feet of concrete storm pipe installed
  • 7 concrete foundations for new decorative streetlights
  • 1,300 linear feet of new concrete curb installed
  • 800 square yards of new concrete sidewalk installed
  • 405 square yards of new brick sidewalk installed

July 20, 2009

Work on the project progressed very well the past two weeks and the project remains on schedule to have the work completed on Braddock and Cameron by the end of October.  The new sidewalks on Braddock Street are shaping up very nicely and have moved all the way from Handley Blvd. to almost Cork Street.  The photos below show some of the initial brick-strip and all brick sidewalks along Braddock.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished past two weeks:

  • 12 sewer laterals replaced (approximately 350 feet of 4-inch PVC pipe)
  • 2 sanitary sewer manhole replaced
  • 87 linear feet of 8-inch+ sewer main
  • 650 linear feet of 8-inch water main installed
  • 10 new water valves installed
  • 49  water service lines replaced (approximately 1,772 linear feet of copper tubing)
  • 3 new fire hydrants installed
  • 12 stormwater structures installed
  • 316  linear feet of concrete storm pipe installed
  • 8 concrete foundations for new decorative streetlights
  • 1,250 linear feet of new concrete curb installed
  • 705 square yards of new concrete sidewalk installed
  • 308 square yards of new brick sidewalk installed

July 6, 2009

We hope everyone had a happy and safe 4th of July.  Crews took Friday afternoon off so that they could spend the long weekend with their families.  The past two weeks on the project were very productive as the water line replacement on Cameron Street has been completed almost to Cork Street and work started on the sidewalk replacements on Braddock Street.  In addition, crews bored and installed the steel casing pipe under Town Run that will be used to install the new water main under the stream.

The photos below show the sidewalk replacements on Braddock near Gerrard and also the bore under Town Run.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished past two weeks:

  • 30 sewer laterals replaced (approximately 1,080 feet of 4-inch PVC pipe)
  • 4 sanitary sewer manhole replaced
  • 260 linear feet of 8-inch sewer main
  • 1,250 linear feet of 8-inch water main installed
  • 10 new water valves installed
  • 19 water service lines replaced (approximately 870 linear feet of copper tubing)
  • 4 new fire hydrants installed
  • 30 linear feet of steel casing pipe under Town Run
  • 12 stormwater structures installed
  • 56 linear feet of concrete storm pipe installed
  • 4 concrete foundations for new decorative streetlights
  • 1,440 linear feet of new concrete curb installed
  • 1,380 square yards of new concrete sidewalk installed

June 22, 2009

Work on the storm drainage infrastructure started last week.  Once the storm drainage infrastructure is installed (where necessary), the sidewalk replacements can begin in that area.  Overall, crews completed another successful week and the project remains on schedule.

The photos below show the installation of new storm drainage inlets.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 19 sewer laterals replaced (approximately 580 feet of 4-inch PVC pipe)
  • 2 sanitary sewer manhole replaced
  • 50 linear feet of 8-inch sewer main
  • 500 linear feet of 8-inch water main installed
  • 12 new water valves installed
  • 14 water service lines replaced (approximately 400 linear feet of copper tubing)
  • 2 new fire hydrants installed
  • 6 stormwater structures installed
  • 70 linear feet of concrete storm pipe installed

June 15, 2009

The relentless rains continued (we’re not complaining because we need the rain) through the week, but the construction crews continued with their excellent progress.  The first section of water main on Braddock Street was successfully pressure tested and disinfected which allowed for the water service line replacements to begin.

The photos below show a new water service line comprised of copper tubing that is connected to the new ductile iron water main.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 18 sewer laterals replaced (approximately 575 feet of 4-inch PVC pipe)
  • 6 sanitary sewer manhole replaced
  • 130 linear feet of 8-inch sewer main
  • 450 linear feet of 8-inch water main installed
  • 14 new water valves installed
  • 15 water service lines replaced (approximately 400 linear feet of copper tubing)

 

June 8, 2009

The contractor completed installing the water main on Braddock Street all the way to Cork and successfully completed pressure testing the new water main between Gerrard and Germain.  Work on Cameron is nearing the intersection of Clifford.  Crews are definitely hoping to see the sun more this week than they did last week!

The photos below show some of the old water pipes in the ground that have been removed and truly show the need for this project.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 10 sewer laterals replaced (approximately 300 feet of 4-inch PVC pipe)
  • 2 sanitary sewer manhole replaced
  • 41 linear feet of 8-inch sewer main
  • 1,300 linear feet of 8-inch water main installed
  • 23 new water valves installed
  • 5 fire hydrant installed

 

June 1, 2009

In spite of a short week (crews took Memorial Day off) and rain every day during the week, the construction crews still accomplished a significant amount of work.  In addition to the City’s work, crews from Shenandoah Gas also started relocating the gas mains near the Cork/Cameron intersection so that the City can install new storm drainage infrastructure.

The photos below show the installation of a new water valve in the intersection of Braddock & Gerrard.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 10 sewer laterals replaced (approximately 270 feet of 4-inch PVC pipe)
  • 1 sanitary sewer manhole replaced
  • 30 linear feet of 8-inch sewer main
  • 1,300 linear feet of 8-inch water main installed
  • 16 new water valves installed
  • 2 fire hydrant installed


May 25, 2009

A beautiful week of weather allowed the contractor to make excellent progress throughout the week.  The new water main installation started on Cameron Street and continued on Braddock.  With the successful completion of the Soap Box Derby on Saturday, crews will now be able to proceed rapidly down the hill on Cameron towards Cork.

The photos below show the first of what will be numerous asphalt repairs for the project.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 14 sewer laterals replaced (approximately 380 feet of 4-inch PVC pipe)
  • 1 sanitary sewer manhole replaced
  • 1,500 linear feet of 8-inch water main installed
  • 22 new water valves installed
  • 1 fire hydrant installed


May 18, 2009

Work on installing a new water main on Braddock Street started last week as seen in the photos below.  Work also continued on replacing sanitary sewer laterals and manholes on both Braddock and Cameron.  The weather during the week was fairly good for construction and the contractor made excellent progress. 

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 18 sewer laterals replaced (approximately 461 feet of 4 and 6-inch PVC pipe)
  • 6 sanitary sewer manholes replaced
  • 70 linear feet of 8-inch sewer main installed
  • 600 linear feet of 8-inch water main installed
  • 7 new water valves installed

 

May 11, 2009
Construction Kicks Into High Gear

The first full week of construction last week proved to be a successful one.  Construction crews became acclimated to working in downtown Winchester and drivers on Braddock and Cameron quickly learned to merge into one lane with minimal traffic backups.

The photos below show the first of the project signs that will be used throughout the project and the continued work on replacing sanitary sewer laterals.

CLICK IMAGES FOR LARGER VIEW

The following summarizes the work accomplished last week:

  • 18 sewer laterals replaced (approximately 400 feet of 4 and 6-inch PVC pipe)
  • 1 sanitary sewer manhole replaced

 

May 4, 2009
Construction Begins!

In spite of receiving some much needed rain, construction “officially” started today! The initial work as seen in the photos below consists of replacing sanitary sewer laterals from the building to the sewer main in the middle of the street.

CLICK IMAGES FOR LARGER VIEW