FY20 Repaving Program

The City of Winchester began its annual street repaving program on Monday, September 9.  The Fiscal Year 2020 program includes repaving on 18 different streets with an overall distance of approximately 10 lane miles (see list and map below). The streets selected for paving are based on an annual review of all streets in the city and criteria that includes the classification of the street, traffic volumes and the current physical condition.

The City’s goal is to complete all of the repaving for the streets on the list this fall before Thanksgiving (weather permitting).  Any work remaining after Thanksgiving will be completed in the spring of 2020.

The total cost of the repaving program this year will be approximately $1 million with the City of Winchester paying half ($500,000).  The other half ($500,000) will be paid with State Revenue Sharing Funds from VDOT. 

Check back often for updates.

FY20 Repaving List

Street From To Length
(Lane Miles)
UPDATES
Shenandoah Avenue Cork Street Eagle Drive 0.92 Completed
Shenandoah Place Shenandoah Avenue Cul-de-sac 0.13 Completed
Shawnee Avenue Cork Street Cul-de-sac 0.66 Completed
Conway Street Ross Street Atwell Avenue 0.14 Completed
Atwell Avenue Berryville Avenue City Limits 0.16 Completed
Chestnut Street Woodstock Lane Berryville Avenue 0.46 Completed
Bellview Avenue Handley Avenue Nester 0.66 Completed
Princess Court Bellview Avenue Cul-de-sac 0.06 Completed
Handley Avenue Meadow Branch Avenue Bellview Avenue 0.72 Completed
Millwood Avenue Pleasant Valley Road Kent Street 1.00 Completed
Mall Boulevard Mall Road Jubal Early Drive 0.49 Completed
Boscawen Street Kent Street East Lane 0.16 Completed
Sharp Street Kent Street East Lane 0.14 Completed
George Street Whittier Avenue Scott Street 0.42 Completed
Scott Street George Street Fox Drive 0.12 Completed
Pondview Drive Fox Drive End 0.38 Completed
Linden Drive Amherst Street Caroline Street 1.44 Completed
Jubal Early Drive Pleasant Valley Road S. Loudoun Street 0.94 Completed
ADDED: Bridgeforth Drive E. Cork Street War Memorial Drive 0.48 Completed
ADDED: War Memorial Drive
(one lane will remain open)
Maple Drive Bridgeforth Drive 0.42 Completed
ADDED: Cameron Street Piccadilly Street Clark Street 0.34 Completed
FY20 TOTAL     10.23  

Map

Sections marked in red are the streets to be repaved.

FY20 Paving Map