Northeast Infrastructure Improvement Project
Between the fall of 2008 and the fall of 2009, the City of Winchester will be undergoing a watermain replacement project along the streets listed below. The project will be conducted in four sections in which one section must be completed before the next section can begin.
- Cork Street Section - Begins at the intersection of Cork Street
and South Loudoun Street and
continues down Cork Street. (9/2/08-10/16/08)
- East Lane/Woodstock Lane Section - Crosses railroad tracks and continues
up East Lane to Woodstock Lane, then continues down Woodstock Lane
to East Street. (10/17/08 - 5/12/09)
- East Street Section - Continues down East Street and goes north to
intersection of Pleasant Valley Road and Berryville Avenue.
(Current work zone - began 5/13/09) - Berryville Avenue Section - Continues down Berryville Avenue to I-81.
Scope of Work by Street top of page
Cork Street |
East Lane |
Woodstock Street |
East Street |
Berryville Avenue |
|
|---|---|---|---|---|---|
| Watermain Replacement | X |
X |
X |
X |
X |
| Water Services* Replacements | X |
X |
X |
X |
X |
| Fire Hydrant Replacements | X |
X |
X |
X |
X |
| Sanitary Sweer Manhole Replacements | X |
X |
X |
X |
X |
| Sanitary Sewer Services Replacements | X |
X |
X |
X |
X |
| Sanitary Sewer Main Replacement | X |
X |
|||
| Sanitary Sewer Lining | X |
X |
X |
X |
|
| New Stormwater System Infrastructure | X |
X |
|||
| Roadway Reconstructions (8" Base and 3" Base Asphalt | X |
X |
|||
| New Curbs | X |
X |
|||
| New Sidewalks | X |
X |
|||
| Sidewalk Replacements | X |
X |
X |
||
| Asphalt Overlay | X |
X |
X |
X |
X |
* Services = Connections from the main water or sewer pipe to the residence or business
Street Closings and Construction Times top of page
- East Street – East Street will be closed completely
until work is finished.
Construction times: Monday through Saturday, 7:00 a.m. - 10:00 p.m.
- Berryville Avenue – One lane of traffic in each direction
will remain open at all times.
Construction times for commercial* areas: 8:00 p.m. – 7:00 a.m.
Construction times for residential** areas: 7:00 a.m. – 10:00 p.m.
*Commerical areas:
1) Between Pleasant Valley and Woodland Avenue
2) Between Fort Collier Road and I-81
**Residential area:
Between Woodland Avenue and Fort Collier Road
Sidewalks top of page
- Sidewalks in the Winchester Historic District will be replaced with brick outlined concrete sidewalks (as installed on Boscawen Street).
- Sidewalks will be added to the north side of Woodstock Lane.
- All existing sidewalks in the project area will be replaced with new concrete sidewalks.
- Sidewalk replacement on Cork Street will be performed by a separate contractor from the water and sewer work. The sidewalk contractor will follow the utility contractor within 3-4 weeks of completion of utility work. At a minimum, eastbound traffic will be maintained on Cork Street during sidewalk reconstruction.
Project Benefits top of page
- Increased water pressure
- Updated water and sewer lines = improved reliability
- New roads
- New sidewalks
Project Contacts top of page
Perry Eisenach, Director of Public Services
667-1815
peisenach@ci.winchester.va.us
Kelly Henshaw, City Engineer
667-1815
khenshaw@ci.winchester.va.us
Drew Brady, Construction Inspector
667-1815
dbrady@ci.winchester.va.us