Northeast Infrastructure Improvement Project

Between the fall of 2008 and the fall of 2009, the City of Winchester will be undergoing a watermain replacement project along the streets listed below.  The project will be conducted in four sections in which one section must be completed before the next section can begin.

  1. Cork Street Section - Begins at the intersection of Cork Street and South Loudoun Street and continues down Cork Street. (9/2/08-10/16/08)
  2. East Lane/Woodstock Lane Section - Crosses railroad tracks and continues up East Lane to Woodstock Lane, then continues down Woodstock Lane to East Street. (10/17/08 - 5/12/09)
  3. East Street Section - Continues down East Street and goes north to intersection of Pleasant Valley Road and Berryville Avenue.
    (Current work zone - began 5/13/09)
  4. Berryville Avenue Section - Continues down Berryville Avenue to I-81.

Scope of Work by Street top of page

 
Cork
Street
East
Lane
Woodstock
Street
East
Street
Berryville
Avenue
Watermain Replacement
X
X
X
X
X
Water Services* Replacements
X
X
X
X
X
Fire Hydrant Replacements
X
X
X
X
X
Sanitary Sweer Manhole Replacements
X
X
X
X
X
Sanitary Sewer Services Replacements
X
X
X
X
X
Sanitary Sewer Main Replacement
X
X
Sanitary Sewer Lining
X
X
X
X
New Stormwater System Infrastructure
X
X
Roadway Reconstructions (8" Base and 3" Base Asphalt
X
X
New Curbs
X
X
New Sidewalks
X
X
Sidewalk Replacements
X
X
X
Asphalt Overlay
X
X
X
X
X

* Services = Connections from the main water or sewer pipe to the residence or business

Street Closings and Construction Times top of page

  1. East Street – East Street will be closed completely until work is finished. 

    Construction times: Monday through Saturday, 7:00 a.m. - 10:00 p.m.

  2. Berryville Avenue – One lane of traffic in each direction will remain open at all times. 

    Construction times for commercial* areas: 8:00 p.m. – 7:00 a.m.
    Construction times for residential** areas: 7:00 a.m. – 10:00 p.m.

    *Commerical areas:  
         1) Between Pleasant Valley and Woodland Avenue
         2) Between Fort Collier Road and I-81
    **Residential area:
          Between Woodland Avenue and Fort Collier Road

Sidewalks top of page

  1. Sidewalks in the Winchester Historic District will be replaced with brick outlined concrete sidewalks (as installed on Boscawen Street).
  2. Sidewalks will be added to the north side of Woodstock Lane.
  3. All existing sidewalks in the project area will be replaced with new concrete sidewalks.
  4. Sidewalk replacement on Cork Street will be performed by a separate contractor from the water and sewer work.  The sidewalk contractor will follow the utility contractor within 3-4 weeks of completion of utility work.  At a minimum, eastbound traffic will be maintained on Cork Street during sidewalk reconstruction.

Project Benefits top of page

  • Increased water pressure
  • Updated water and sewer lines = improved reliability
  • New roads
  • New sidewalks

Project Contacts top of page

Perry Eisenach, Director of Public Services
667-1815
peisenach@ci.winchester.va.us

Kelly Henshaw, City Engineer
667-1815
khenshaw@ci.winchester.va.us

Drew Brady, Construction Inspector
667-1815
dbrady@ci.winchester.va.us