Current City Projects

Residential Developer Projects

Scroll down for City of Winchester projects.

(Updated 7/20/23)

Projects In Progress Ward Location Rezoning/CUP
Approval Status
Site Plan
Approval Status
Comments # Units
Cameron Square
(Apartments)
2 200-300 Block N. Cameron St CU-20-666, 10/12/21 Filed 2/18/22 Pending site plan approval 171
Cameron/Gerrard Street
(Apartments)
2 819 S. Cameron St N/A Approved 9/15/22 Under construction 8
Creekside Condos 4 3131 Valley Ave RZ-18-893, 2/26/19 Approved 6/27/22 Site work started, permits issued 45
Crossover Apartments 3 200-block Crossover Blvd RZ-22-275, 9/27/22 Not yet filed Not started 331
Hackwoods SVWC
(Senior housing)
1 654 Fox Dr RZ-20-371, 10/13/20 Approved 3/18/22

Site work & buildings under construction

39
Hampton Manor Nursing 4 940 Cedar Creek Grade CU-21-529, 9/28/21 Approved 4/8/22 Buildings under construction, site work continues 107
Harrison Plaza (Apartments) 4 Valor Drive/Taft Ave/Hope Dr RZ-19-413, 8/27/19 Approved 3/12/20 One building complete, 2 buildings under construction 70
Laurelwood Commons
(Townhouses)
2 520 N. Pleasant Valley Rd RZ-21-931, 3/22/22 Site plan pending Not started 34
Linden Drive 1 441 Linden Dr RZ-22-162, 6/14/22 Not yet filed Former school demolished/remediation 18/296
Meadow Branch Phase 2 1 520 Meadow Branch Ave RZ-20-67, 5/26/20 Approved 4/23/21 All six buildings under construction
(1st phase close to occupancy)
134
N. Kent Properties
(Winchester Star building)
2 2 N. Kent Street N/A Approved 5/11/22 Nearing completion 5
Old Hospital Senior Living Center 1 333 W. Cork St CU-18-815 Approved 3/12/20 Asbestos abatement underway 195
Piccadilly Townes
(Condos)
2 E. Piccadilly St & N. Kent St N/A Approved 2/11/22 Under construction 16
Roberts Square (Apartments) 4 1811 Roberts St RZ-20-272, 10/27/20 Not yet filed Expecting resubmittal soon 36
Schwartz Family Towns
(Townhouses)
3 229 S. Pleasant Valley Rd RZ-21-906, 3/8/22 Not yet filed Not started 25
Smalts area 2 400-block National Ave RZ-22-638, 12/13/22 Not filed yet Not started 51
Tevis Townhouses 4 375 W. Tevis St RZ-21-30, 4/27/21 Approved 1/10/22 Plan revised to add garages 20
The Local (Apartments) 3 230 Spring St RZ-20-379, 1/26/21 Approved 10/21/21 Garage complete, building framing started 198
Treetops Apartments, Phase 2 4 501 Treetops Ln RZ-18-923, 3/26/19 Submitted No Action 18
Winchester Commons
(Apartments)
3 2210 Legge Blvd RZ-21-591, 11/23/21 Approved 3/15/23 Not started 246
Winchester Grove (Apartments) 4 Valley Ave & Hillman Dr RZ-22-108, 4/26/22 Anticipate filing soon Not started 440
ZeroPak 2 536-580 N. Cameron St CU-22-945, 2/28/23 Not filed yet Not started 122
550 Fairmont
(Apartments & Townhouses)
1 Fairmont Ave & Wyck St RZ-22-379, 8/9/22 Not yet filed Not started 262
3-5 Apartments 1 33-39 W. Boscawen St N/A Close to approval Asbestos abatement underway 12
TOTAL UNITS           18 Single Family
2,898 Units

PUD = Planned Unit Development   RZ = Rezoning    CU = Conditional Use


City-Funded Capital Projects

Click here for a list of scheduled road closures (project-related and others).

(Updated 12/19/22)

City Gov't Projects In Progress Est. Construction Start Est. Completion Project Details
FY23 Sidewalk Replacements August 8, 2022 TBD 1. N. Braddock Street (Fairfax to Wyck)
2. E. Boscawen Street (Kent to East Ln)
3. N. Kent Street (Cork to Piccadilly)
4. Parkway Street (Cork to Hollingsworth)
5. Greystone Terrace (Millwood to cul-de-sac)
Central Downtown Infrastructure Improvements 2020 TBD Link
Valley Avenue Improvements January 11, 2021 TBD $9M (Valley Ave) - Link
Douglass Park Improvements October 2022 Spring 2023 Field grading, irrigation system, grass, new restrooms, lighting
New at N. Loudoun/Brooke/Brick Kiln Spring 2023 Spring 2023 Replacement of existing traffic signal

 

City Gov't Projects In Design Phase Cost Project Details
Preston Field Improvements (Jim Barnett Park) $2.3M Construction of two full-size artificial turf soccer fields. RFP to be sent in Dec. 2022.
Millwood Avenue Improvement Project $6.5M Link
Council has approved the City's portion of the project. VDOT will be managing it since Rt. 50 bridge replacements over I-81 will be happening at the same time. Construction expected to begin in early 2025.
Green Circle Trail - Phase IV  $5.4M Link
Abrams Creek route option was approved by Council. Final design is in progress.
N. Cameron Drainage Improvements (multi-phase project) $14.9M Final design work is in progress. Construction bids to be advertised in spring 2023. Construction is expected to begin in summer 2023.
Traffic Signal Replacement at N. Loudoun/Brooke/Brick Kiln Intersection $580,000 Awaiting VDOT approval to advertise project for bids.
New South End Fire Station TBD First City-owned station. Design effort to begin in January 2023.

 

ARPA Allocations

The City's FY22-23 ARPA Spending Plan ($12,337,682) includes projects addressing:

  • public health
  • negative economic impacts
  • essential worker pay
  • infrastructure improvements
  • digital services upgrades
  • equipment
  • PPE
  • new fire station and firefighters
  • grocery market study
  • bikeshare program
  • facility improvements (indoor pool, security, northside community center, athletic field turf, etc.)
  • more

Completed Capital Projects

New Public Services Facility at City Yards

Eagles Field (Jim Barnett Park) Drainage Improvements

Sidewalk Repair Program

New Traffic Signal at Adams Dr/Legge Blvd

Wentworth Drive Improvements (Safe Routes to School and underground utilities)

Green Circle Trail Phase III (Jubal Early Drive)

Handley Library HVAC Improvements, roof and structural repairs ($2.6M)

New paystations and access gates at all four downtown garages (Parking Authority)

Water Meter & Sidewalk Replacement Project

North Cameron Drainage Improvements (Phase I)

North End Sidewalk Improvements ($1M CDBG Grant)

Live Fire Training Facility 

City Hall Renovation

Kent Street & Woodstock Lane Improvement Projects

Tevis Street Extension

Winchester Towers Demolition & Redevelopment (City's portion)