Current City Projects

Residential Developer Projects

Scroll down for City of Winchester projects.

(Updated 9/15/22)

Projects In Progress Ward Location Rezoning/CUP
Approval Status
Site Plan
Approval Status
Comments # Units
Cameron Square
(Apartments)
2 200-300 Block N. Cameron St CU-20-666, 10/12/21 Filed 2/18/22 Revisions requested 171
Cameron/Gerrard Street
(Apartments)
2 819 S. Cameron St N/A Approved 9/15/22 Under construction 8
Creekside Condos 4 3131 Valley Ave RZ-18-893, 2/26/19 Approved 6/27/22 Site work started 45
Crossover Apartments 3 200-block Crossover Blvd RZ-22-275, pending Not yet filed Not started 331
Hackwoods SVWC
(Senior housing)
1 654 Fox Dr RZ-20-371, 10/13/20 Approved 3/18/22

Site work & foundation under construction

39
Hampton Manor Nursing 4 940 Cedar Creek Grade CU-21-529, 9/28/21 Approved 4/8/22 Site work underway 107
Harrison Plaza (Apartments) 4 Valor Drive/Taft Ave/Hope Dr RZ-19-413, 8/27/19 Approved 3/12/20 All 3 buildings under construction 70
Laurelwood Commons
(Townhouses)
2 520 N. Pleasant Valley Rd RZ-21-931, 3/22/22 Site plan pending Not started 34
Linden Drive 1 441 Linden Dr RZ-22-162, 6/14/22 Not yet filed Former school demolished/remediation 18/296
Meadow Branch Phase 2 1 520 Meadow Branch Ave RZ-20-67, 5/26/20 Approved 4/23/21 All six buildings under construction 134
Old Hospital Senior Living Center 1 333 W. Cork St CU-18-815 Approved 3/12/20 Asbestos abatement started 195
Piccadilly Townes
(Condos)
2 E. Piccadilly St & N. Kent St N/A Approved 2/11/22 Under construction 16
Roberts Square (Apartments) 4 1811 Roberts St RZ-20-272, 10/27/20 Not yet filed Developer revamping layout 36
Schwartz Family Towns
(Townshouses)
3 229 S. Pleasant Valley Rd RZ-21-906, 2/8/22 Not yet filed Not started 25
Smalts area 2 400-block National Ave RZ-22-638, pending Not filed yet Not started 57
Tevis Townhouses 4 375 W. Tevis St RZ-21-30, 4/27/21 Approved 1/10/22 Site work starts soon 20
The Local (Apartments) 3 230 Spring St RZ-20-379, 1/26/21 Approved 10/21/21 Under construction, parking garage near finished 198
Treetops Apartments, Phase 2 4 501 Treetops Ln RZ-18-923, 3/26/19 Submitted Still working on stormwater plan 18
Winchester Commons
(Apartments)
3 2210 Legge Blvd RZ-21-591, 11/23/21 Site plan pending Not started 246
Winchester Grove (Apartments) 4 Valley Ave & Hillman Dr RZ-22-108, 4/26/22 Not yet filed Not started 440
550 Fairmont
(Apartments & Townhouses)
1 Fairmont Ave & Wyck St RZ-22-379, 8/9/22 Not yet filed Not started 262
3-5 Apartments 1 33-39 W. Boscawen St N/A Close to approval Asbestos abatement underway 12
TOTAL UNITS           18 Single Family
2,760 Units

PUD = Planned Unit Development   RZ = Rezoning    CU = Conditional Use


City-Funded Capital Projects

Click here for a list of scheduled road closures (project related and others).

City Gov't Projects In Progress Est. Construction Start Est. Completion Project Details
FY23 Sidewalk Replacements August 8, 2022 TBD
(Braddock will take approx. 8 weeks)
1. N. Braddock Street (Fairfax to Wyck)
2. E. Boscawen Street (Kent to East Ln)
3. N. Kent Street (Cork to Piccadilly)
4. Parkway Street (Cork to Hollingsworth)
5. Greystone Terrace (Millwood to cul-de-sac)
Central Downtown Infrastructure Improvements 2020 TBD Link
Hope Drive Extension, Tevis Cul-de-sac & Valley Avenue Improvements January 11, 2021 Fall 2022 $8.3M (Hope Drive) & $9M (Valley Ave)
Link
New Public Services Facility at City Yards Fall 2020 Fall 2022 $11.2M
Equipment storage & admin buildings
City-wide Street Repaving ($2M) Summer 2022 TBD Currently underway. Approx. 90% completed.
Douglass Park & Eagles (Jim Barnett Park) Field Improvements October 2022 TBD Improve field drainage, quality and amenities

 

City Gov't Projects In Design Phase Cost Est. Construction Start Project Details
Millwood Avenue Improvement Project $6.5M TBD Link
Council has approved the City's portion of the project. VDOT will be managing it since Rt. 50 bridge replacements over I-81 will be happening at the same time.
Green Circle Trail - Phase IV  $5.4M TBD Link
Currently soliciting public feedback. Options presented to PED Committee on 4/28/22. Abrams Creek route was approved by Council. Final design is in progress.
N. Cameron Drainage Improvements (multi-phase project) $14.9M TBD Final design work is in progress. Acquisition of CSX parcels needed to construct stormwater management ponds has been completed. Construction is expected to begin in summer 2023.
Traffic Signal Replacement at N. Loudoun/Brooke/Brick Kiln Intersection $580,000 TBD Awaiting VDOT approval to advertise project for bids.
Douglass Park Improvements $500,000 TBD Contract awarded. Work to begin in October 2022.
Eagles Field Drainage Improvements $150,000 TBD Contract signed. Work to begin in October 2022.

 

ARPA Allocations

The City's FY22-23 ARPA Spending Plan ($12,337,682) includes projects addressing:

  • public health
  • negative economic impacts
  • essential worker pay
  • infrastructure improvements
  • digital services upgrades
  • equipment
  • PPE
  • new fire station and firefighters
  • grocery market study
  • bikeshare program
  • facility improvements (indoor pool, security, northside community center, athletic field turf, etc.)
  • more

Completed Capital Projects

Sidewalk Repair Program

New Traffic Signal at Adams Dr/Legge Blvd

Wentworth Drive Improvements (Safe Routes to School and underground utilities)

Green Circle Trail Phase III (Jubal Early Drive)

Handley Library HVAC Improvements, roof and structural repairs ($2.6M)

New paystations and access gates at all four downtown garages (Parking Authority)

Water Meter & Sidewalk Replacement Project

North Cameron Drainage Improvements (Phase I)

North End Sidewalk Improvements ($1M CDBG Grant)

Live Fire Training Facility 

City Hall Renovation

Kent Street & Woodstock Lane Improvement Projects

Tevis Street Extension

Winchester Towers Demolition & Redevelopment (City's portion)