South End Fire Station

South End Fire Station (1).png

The City of Winchester is building a new South End Fire Station at the site of the current South End Fire Station at 17 W. Monmouth St. The existing facility will be kept fully operational during the three phase construction of the new station. 

This new state of the art fire station will be 26,000 square feet across two stories and will seek LEED Silver certification. There will be four apparatus bays entering onto S. Braddock Street, a three story hose tower for hose storage and firefighter training purposes, and a second floor patio for firefighter use. 

Construction Phase 1

  • Install perimeter construction fencing with super silt fence attached. 
  • Install construction entrance at the existing parking lot along W. Monmouth St. 
  • Install temporary construction trailer in the existing along W. Germain St. 
  • Delineate the temporary parking lot within the area hatched light yellow.
  • Maintain an ADA accessible route within the area hatched light red. 

South End Phase 1.png

Construction Phase 2

  • Disconnect existing utilities not servicing the remaining portion of the fire station. 
  • Demolish existing "bingo hall" portion of the existing fire station within the area hatched dark brown. 
  • Demolish existing auto repair building within the area hatched dark brown. 
  • Demolish existing parking lot along W. Monmouth St. within the area hatched light brown. 
  • Demolish existing miscellaneous surface features within the are hatched light brown. 

South End Phase 2.png

Construction Phase 3

  • Install a new construction entrance along W. Germain St. 
  • Prepare a "construction lay down area" within the area hatched dark blue. 
  • Construct the new fire station building. 
  • Construct the site improvements along S. Braddock St. and a portion of the frontage along W. Monmouth St. 

South End Phase 3.png

Construction Phase 4

  • Disconnect existing utility services to the remaining portion of the existing fire station. 
  • Demolish remaining portion of the existing fire station within the area hatched dark brown. 
  • Demolish a portion of the existing parking lot within the are hatched light brown. 
  • Maintain 12 standard parking spaces within the area hatched light yellow. 
  • Reserve on HC parking space as shown along S. Braddock St. 

South End Phase 4.png

Construction Phase 5

  • Construct proposed parking lot within the area hatched dark gray. 
  • Demolish remaining portion of the existing parking lot within the area hatched light brown. 

South End Phase 5.png